CONSTRUCTION OF STAGES 4-6 STARTED

Posted by Khurram Saeed on Jan 25, 2019 8:01:00 AM


Screen Shot 2019-01-23 at 3.01.43 pm

The Accolade team is pleased to announced that Bitu-mill is forging ahead and construction has commenced Stages 4-6 with titles expected from Qtr 3 2019 onwards.
Stages 4 & 5 - Site clean-up is 100% complete after the demolition of an old house and sheds on-site, and Bulk Earthworks & Stripping are now 80% complete.
Stage 6 - Preliminary work has commenced with Stripping and Bulk Earthworks 10% complete.

A video update will come in early February.

Topics: #landdevelopmentagreements, #LDA, #resiventures, #rockbank, #accolade, #funding, construction