The team in conjunction with Bitu-mill is very proud to see construction progressing strongly at Accolade. Stage 1 – Civil phase is 55% complete, Stage 2 – Civil phase is over 40% complete, while Stage 3 Civils are 35% complete. Titles for Stages 1 to 3 should be delivered in Q2 2019.