ACCOLADE CONSTRUCTION UPDATE

Posted by Khurram Saeed on Jan 8, 2019 6:03:04 PM

The team in conjunction with Bitu-mill is very proud to see construction progressing strongly at Accolade.  Stage 1 – Civil phase is 55% complete, Stage 2 – Civil phase is over 40% complete, while Stage 3 Civils are 35% complete.  Titles for Stages 1 to 3 should be delivered in Q2 2019.

 

 

 

 